The latest from Eryl onsite

Two separate concrete pours are required to construct the base. More than 50,000m³ will be used across the turbine bases, with an average of 600m³ per base.

Eryl Roberts, project manager for the Jones Bros and Balfour Beatty joint venture, gives us an update on how the construction of the wind farm’s turbine bases is progressing.

“Work is progressing well on site. We’re very happy with how everything is going, and the recent hot weather has made a world of difference.

Read more…