Grid connection works continue

IMG_7423

Transformer deliveries on Sunday April 19th and 26th 2015

Our contractors ABB continue with the grid connection works. The next step this month is the installation of two transformers that will enable the power from the wind turbines to be injected into the National Grid.

Read more…

Considerate Constructors at PyC

CCSaward2

The Pen y Cymoedd Wind Energy Project has won a national award that recognises efforts made by the construction industry to be considerate neighbours. The windfarm project has won a Considerate Constructors Scheme award, recognising the efforts of the project’s developers to be sympathetic to the local community. The awards judge construction projects on five criteria to determine whether site team have acted in a responsible and considerate way towards local residents and site users. To deliver the project Vattenfall is working with contractors Jones Bros/Balfour Beatty who are responsible for the civil works.

Read more…