Turbine component deliveries – week commencing 29th February

Lorry line up

Please see below turbine component delivery information for the week commencing 29th February. With the weather in an improved state at the moment, deliveries will continue as they have been over the last few weeks. Please note that these are expected times only. Please get in touch if further information is required.

Read more…

Turbine installations – some facts!

3rd pre assembly

As of Friday last week, 105 of 684 abnormal loads had been successfully delivered to the site from Swansea Docks. Later this week we expect our contractor to begin delivering the turbine blades to site in convoys of up to three abnormal loads. Each blade is the lightest component at 11.3 tonnes, yet the longest component at 55 metres.

Read more…

Turbine component deliveries – week commencing 22nd February

Turbine component deliveries

Please see below turbine component delivery information for the week commencing 22nd February. With the weather in an improved state at the moment, deliveries will continue as they have been over the last few weeks. Please note that these are expected times only. Please get in touch if further information is required.

Read more…

Turbine tower installations continue

3rd pre assembly

We expect to install the first two tower sections of up to six turbines this week (weather dependent). The tower stumps that will be installed are known as the pre-assembly for each turbine. The remainder of the turbine components for each turbine in the Spring and Summer of this year.

Turbine component deliveries – week commencing 15th February

Siemens deliveries at Lochluichart Wind Farm, Inverness, Scotland

Please see below turbine component delivery information for the week commencing 15th February. With the weather in an improved state at the moment, deliveries will continue as they have been over the last few weeks. Please note that these are expected times only. Please get in touch if further information is required.

Read more…