Construction – What’s happening when?

Turbines being installed at Vattenfall's Swinford Wind Farm

February 2014 – 2016: Civil and electrical works, including construction of the site welfare compound, site access tracks, turbine foundations, crane pads, underground cabling and substation

Late 2015: Turbine deliveries, civil works continue

Early 2016: Turbine installation expected to begin

Late 2016: The wind farm is commissioned

Early 2017: Project completion