Our neighbours are installing turbines

IMG_2124

Our neighbours at Mynydd Bwllfa are currently installing turbines. This 22.5MW, 9 turbine development received planning consent in May 2012 and construction began in November 2013. The project is due for completion in the summer of 2015. You can find out more about the project and sign up for updates here.

At Pen y Cymoedd our project timeline remains on track. Our turbine component deliveries are due to commence in late 2015, with turbine installations due to commence in early 2016. With half of the turbine foundations complete our construction team continue to get the site ready for the upcoming turbine deliveries. Due to the adverse winter weather the team had a break from constructing turbine foundations, focusing on access tracks. Work on the foundations resumed this week ready for the steel fixing team to resume works next month.

Don’t forget to sign up here for an upcoming site visit to see the construction works with your own eyes.