Turbine component deliveries – week commencing 31st May

5

Please see below turbine component delivery information for the week commencing 31st May. Please note that these are expected times only. Please get in touch if further information is required.

Morning deliveries are expected to leave Swansea Docks at around 09:30. Due to the length of time it takes for the components to travel to their respective turbine locations, we cannot be specific regarding the afternoon delivery time, and deliveries will leave Swansea Docks between 11:30 and 13:30. This means they will arrive at the bottom of the Rhigos between 12:30 and 14:30.

Read more…

Turbine component deliveries – week commencing 22nd February

Turbine component deliveries

Please see below turbine component delivery information for the week commencing 22nd February. With the weather in an improved state at the moment, deliveries will continue as they have been over the last few weeks. Please note that these are expected times only. Please get in touch if further information is required.

Read more…

Turbine component deliveries – week commencing 1st February

Turbine component deliveries

Please see below turbine component delivery information for the week commencing 1st February. Please note that these are expected times only. Please get in touch if further information is required.

Morning deliveries continue this week, leaving Swansea Docks at around 09:30. Due to unpredictable fog on the Rhigos Mountain, we cannot be specific regarding the afternoon delivery time, and deliveries will leave Swansea Docks between 11:30 and 13:30. This means they will arrive at the bottom of the Rhigos between 12:30 and 14:30. We will attempt to post more up to date information on Facebook and Twitter.

Read more…

Vattenfall looks back on a successful 2015 at Pen y Cymoedd

Eryl Roberts and Jason Osborne from Jones Bros Balfour Beatty Joint Venture.jpg

Fantastic progress continues at England and Wales’ largest onshore wind farm

Vattenfall, the European energy company, and their contractors building Wales’ largest onshore wind farm, are looking forward to a relaxing Christmas as the last of the scheme’s 76 wind turbine foundations are completed this week.

Read more…