Turbine component deliveries underway

Siemens deliveries at Lochluichart Wind Farm, Inverness, Scotland

Siemens, our turbine supplier, commenced the turbine component deliveries this morning, Monday 30th November. The first convoy of three lorries and associated escort vehicles, left Swansea Docks at 09:30am. It is expected to take around one hour to reach the A4061, Rhigos Road where the convoy will be joined by a police escort. Delays are possible and we apologise for any inconvenience caused.

Thereafter, we expect one convoy of up to three lorries per day to take place between 09:30 and 15:00, Monday to Saturday, until the site closes for Christmas on 18th December.

In the new year we expect two convoys of up to three lorries per day to be delivered to site, one in the morning and one in the afternoon.

Delivery times are subject to change and we will do our best to publish up to date information on this blog, Facebook page and Twitter feed. Please get in touch with any queries.