Please see below turbine component delivery information for the week commencing 14th December. Please note that these are expected times only. Please get in touch if further information is required.

Monday 14th December – one convoy of up to three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Tuesday 15th December – one convoy of up to three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Wednesday 16th December – no deliveries today.

Thursday 17th December – no deliveries today.

Friday 18th December – one convoy of up to three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

After this week the site will close for the Christmas period. Deliveries are expected to recommence on 4th January 2016.