Turbine component deliveries – week commencing 30th November

Siemens deliveries at Lochluichart Wind Farm, Inverness, Scotland

Monday 30th November – one convoy of three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Tuesday 1st December – one convoy of three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Wednesday 2nd December – one convoy of three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Thursday 3rd December – one convoy of three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Friday 4th December – one convoy of three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Saturday 5th December – one convoy of three lorries expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

The status of the above is subject to change and we will publish updated information on this blog, our Twitter feed and Facebook page. We apologise in advance for any delays or inconvenience caused. For more information view this short film in English or Welsh, or download a fact sheet.

For queries please contact Emily Faull on 02921 303400 or penycymoedd@vattenfall.com.