Turbine component deliveries – week commencing 3rd October

IMG_0865

Please see below turbine component delivery information for the week commencing 3rd October. Please note that these are expected times only. Please get in touch if further information is required.

Morning deliveries are expected to leave Swansea Docks at around 09:30.

Monday 3rd October – Convoy one is expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Tuesday 4th October – Convoy one is expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Wednesday 5th October – Convoy one is expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Thursday 6th October – Convoy one is expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Friday 7th October – Convoy one is expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

Saturday 8th October – Convoy one is expected to leave Swansea Docks at 09:30, arriving on Rhigos Road at approximately 10:30. The delivery is expected to leave the public highway at the Tower Colliery forestry entrance by 11:00.

The status of the above is subject to change. We apologise in advance for any delays or inconvenience caused.

For queries please contact Emily Faull on 02921 303400 or penycymoedd@vattenfall.com.

Photo credit: Mike Davies.